Edit Vertices mode
To enter Edit Vertices mode, either select the shape and hit enter twice or select a path and hit enter once.
Deep Selection
You may want to select and edit a specific path when dealing with a group of shapes. You can either find that path in the Hierarchy or you can use Deep Selection to select it directly on the Stage. To select a path within a group on the stage, hold⌘ (Mac) or ctrl (Windows) and click the target path. Alternatively, you can double-click on the path you want to select.
Path Options
Each path in Edit Vertices mode has a set of path options at the top of the Inspector. Done Editing Button The Done Editing button can be used to exit Edit Vertices Mode.


Bezier Handles
Straight The default handles are set to straight, which creates straight edges between vertices.